A Scott Schedule template should match the directions in your case. Start with the relevant official form, then organise the disputed items and supporting evidence around it. This guide explains NCAT’s defective workmanship form and practical ways to keep the schedule consistent with an expert report.
What is a Scott Schedule?
A Scott Schedule is a table that brings the parties’ positions on individual building issues together. It can record the contractual requirement, alleged defect, response and loss claimed. The detailed evidence is cross-referenced so the entries can be checked.
Follow the form and directions for the matter
NCAT provides Scott Schedule forms for defective workmanship and for variations or extras on its Consumer and Commercial Division forms page. Confirm which form, columns and exchange process the directions require. A generic nine-column layout should not be treated as the required format for every NSW claim.
Fields in NCAT’s defective workmanship form
The official defective workmanship form identifies these fields. This table explains them; use NCAT’s current document for the actual schedule.
| Field | Purpose |
|---|---|
| Item number | A stable reference for the issue. |
| Contract | The work required under the contract or the workmanship required to complete it. |
| Applicant comments | The alleged defect. |
| Applicant loss estimate | The claimed rectification cost or reduction in value. |
| Respondent comments | The response to the allegation, including any legal point raised. |
| Respondent loss estimate | The respondent’s assessment, completed even where liability is denied. |
| Member comments | Reserved for the Tribunal Member. |
Denying liability does not, by itself, justify entering “nil” or “not applicable” in the respondent’s estimate. Explain the assessment and its basis while keeping the liability position separate. Do not complete the Member’s field on the Member’s behalf.
Add useful detail without obscuring the required fields
Location, report paragraph, photograph and costing references can help identify the issue. Include them within the permitted layout or seek directions if a different structure is needed. Keep descriptions concise and use references for the detailed reasoning.
Check the entries before exchange
- Use consistent item numbers across the schedule, report and photographs.
- Separate distinct issues where they require different findings or repair scopes.
- State the evidence for the alleged defect, rather than assuming the symptom proves a cause.
- Explain cost quantities, rates, allowances and any qualifications.
- Distinguish agreement on a defect from agreement on scope and cost.
- Track amendments and follow the directions about exchanging and filing versions.
For example, a respondent may accept that water entered a room but dispute the proposed cause, extent of demolition or repair price. Record those positions separately and refer to the evidence for each.
Connect the schedule to the expert report
The report explains observations, reasoning and limitations; the schedule summarises the position on each item. Retain qualifications when shortening an opinion. A tentative finding should not become an absolute statement in a table.
Confirm the applicable expert code and orders. For NCAT, consult Procedural Direction 3; court proceedings may have different requirements.
Identify locations clearly in strata matters
Use building, level, lot and common-area references so each item can be located. Identify documents relevant to the work and obtain legal advice on the proper claimant, respondent and legal basis; the physical location alone does not decide liability.
Agree the preparation scope
Clarify whether you need help organising existing evidence, a new investigation, an expert response or a cost assessment. A schedule cannot replace investigation needed to support a technical opinion.
Frequently asked questions
Is there an official template?
Yes. NCAT publishes forms for different schedule purposes. Obtain the relevant version from the official forms page and follow the directions in your matter.
Must every schedule include separate expert columns?
No universal extra-column arrangement applies to every case. Use the directed format and cross-reference the expert report appropriately.
Can the respondent leave the loss estimate blank when denying liability?
The defective workmanship form calls for that assessment even where liability is denied. Keep the response to the allegation distinct from the estimate.
What if an item needs further investigation?
Identify the missing evidence or access issue and explain any limits on the current position. Follow the timetable and seek directions where further work affects compliance.
Request help with your schedule