A Scott Schedule brings individual building dispute items into one table so that the parties’ positions can be compared. This guide concerns NSW court proceedings. The document supports the presentation of a case; listing a defect or a repair figure does not, by itself, establish that claim.

When can a NSW court require a Scott Schedule?

The NSW Online Registry’s Scott Schedule guidance refers to UCPR 15.2 and form 13. It explains that a claimant may file a schedule in proceedings involving multiple disputed items, and that the court may order one. A party served with it must respond to the items and identify any amount conceded, where appropriate.

Check the orders, applicable practice note and current court form before starting. Record the dates for preparation, response, filing and service. An NCAT template should not automatically be substituted for the court’s required format.

Keep each disputed item traceable

Use the prescribed columns. As a practical drafting approach, make it possible to identify the location, alleged problem, relevant contractual requirement, proposed rectification and basis of the amount claimed. Keep the same item numbers in the schedule, reports, photographs and document index.

A response should explain which parts of an item are accepted or disputed. Distinguish an assessment of repair cost from an amount conceded and from any settlement proposal. Leave any section reserved for the court to the court.

Separate the defect, scope and cost questions

Agreement that a defect exists does not necessarily mean agreement about how to repair it or what the repair should cost. For each building issue, consider these questions separately:

  • Defect: What was observed, and what requirement is said to have been breached?
  • Scope: What work is proposed, why is it necessary, and are there reasonable alternatives?
  • Cost: Which quantities, rates, quotations or invoices support the amount?

Identify assumptions, inaccessible areas and further testing needed. Where work has already been completed, distinguish the actual work and invoices from any earlier proposed repair scope. Avoid adding the same repair cost under several items.

Reference the supporting evidence

A short reference to a report paragraph, photograph number or drawing detail is more useful than repeating a lengthy report in each cell. Keep an indexed set of the underlying documents available, and follow the court’s directions about the evidence to be filed and served.

Use expert opinions within their proper scope

An expert’s assessment should explain the technical reasons for the opinion, including qualifications or limitations. An expert’s role is independent assistance to the court, rather than advocacy for the person paying the fee. See the official expert witness code of conduct and duties.

A Scott Schedule, an expert report and a joint expert report serve different purposes. Confirm which documents the orders require and how they should refer to one another. For an NCAT matter, use the separate NCAT format guide and the Tribunal’s current directions.

Illustrative working example

The following is an unpriced drafting example, not an actual case, a court finding or an official court form.

ItemInformation to identify
1. Water entry at a windowLocation and observed symptoms; report and photograph references; each party’s position; proposed repair and cost evidence.
2. Uneven floor finishMeasured variation and relevant requirement; disputed extent; repair alternatives; quantities and pricing assumptions.

Complete the actual schedule using the required form and the evidence in your matter. A well-organised schedule can clarify the remaining disagreements, but does not guarantee settlement or a particular result.

Discuss preparation with Awesim

For a fee proposal, provide the court orders, existing schedule, expert reports, photographs and relevant contract documents. Include the next deadline and whether assistance is needed with an initial schedule, a response or expert conferencing.

Read about Awesim’s Scott Schedule services or request a consultation.

author avatar
Glen Sim Managing Director
Glen Sim is the Founder and Director of Awesim Building Consultants. He is a qualified carpenter, licensed builder and building expert witness with more than 35 years of construction experience. Based in New South Wales, he provides building consultancy, expert witness reports, Scott Schedules and building defect inspections across Australia, including support for NCAT building disputes in NSW.

Share the Post:

Scroll to Top